Qinshan Nuclear Power Plant 

Construction of the first indigenously designed 300 MWe pressurized water reactor started in Qinshan, Zhejiang on March 20, 1985. The reactor was successfully connected to the power grid on December 15, 1991. The completion of this project marked the beginning of China's nuclear power development and was celebrated as "a proud achievement". Since the unit was put into operation, more than 130 technical modifications have been made to turn the prototype reactor into a commercial reactor. The reactor has an impressive record of safe continuous operation for 469 days. Its 18.12-day overhaul time is the shortest in China. And it has improved its ranking in WANO composite index year by year and ranked first in the world twice among similar units. 

秦山核電站
Qinshan NPP

秦山核電站 

1985年 3月 20日,中國自主設(shè)計、自主建造、自主運(yùn)營的第一座 30萬千瓦壓水堆核電站在浙江秦山開工建設(shè),1991年 12月 15日成功并網(wǎng)發(fā)電。秦山核電站的建成,結(jié)束了中國大陸無核電的歷史,標(biāo)志著“中國核電從這里起步”,被譽(yù)為“國之光榮”。該核電機(jī)組投入運(yùn)行后,先后完成 130多項技術(shù)改造,成功將一個原型堆改進(jìn)為商用堆,并創(chuàng)造了連續(xù)安全運(yùn)行 469天的優(yōu)異成績和 

18.12天國內(nèi)核電大修最短工期記錄,世界核電運(yùn)營者協(xié)會(WANO)綜合指數(shù)排名逐年提高,曾兩次位列同類機(jī)組世界第一。